Testing continues for Knurr Cool Therm

Testing continues for the Knurr CoolTherm rack.  Several metering issues arose during the first week and a half of testing that have been identified and mostly resolved.  The last issue (flow meter reporting) is being resolved today (6/12).  We expect to continue with official testing next week and are targeting Friday (6/19) or Monday (6/22) to complete the CoolTherm test.   Given our experience with Chill Off 1, we expected the first test to take the longest to get set up as we work through the various issues with connecting and testing all of the components.  However, now that the test environment is becoming much more stable, we expect to move through the remaining tests more efficiently.  I am adjusting the schedule accordingly and will post updated time frames for the other tests next week.