Second Chill Off Test Completed!

I am very happy to announce that we finished our second test in the Chill Off project today!  The Knurr CoolLoop solution testing was successfully completed this evening.  We will be quickly moving to our third and fourth tests (Rittal and IBM/Vette) which have already been pre-staged in the test area.  We will be making the final mechanical/electrical connections and moving the IBM Blade Centers over Thursday.  We will verify the Rittal system is operational Friday and hope to get a bake in period that same day.  If all goes well we will be done with our third test by early to mid next week!  I'm updating the rest of the schedule now that we've successfully completed the second test and have a more accurate time frame to use as an assumption for the rest of the tests.  I will publish the updated schedule dates to the rest of the participants by the end of this week or early next week.  As always, feel free to ask any questions; brian.day@datacenterpulse.org.