Chill Off 2 - Schedule Update

Hi folks, I am still working on the overall schedule for the Chill Off 2. Right now we are looking at getting testing kicked off in early April and continuing through July. The ordering I’m looking at right now is:

1) Knuerr Cool Therm
2) Rittal Enclosed (2 rack config)
3) IBM Integrated Solution
4) IBM Rear Door Solution
5) Knuerr Cool Loop (2 rack config)
6) Knuerr Cool Loop (8 rack config)
7) APC Rack Containment
8) APC Hot Aisle Containment (8 rack config)
9) Sun Glacier (refrigerant)
10) Clustered Systems (refrigerant)
11) Liebert Forced Air (8 rack config)
12) Sun MD (8 rack config - in parallel to the others above)

In the meantime, we are continuing the mechanical/electrical/network setup of the room with 3/30 as the target for beginning to connect up the Knuerr Cool Therm solution.

Stay tuned this week for more updates… Brian