Hi folks, sorry it has taken me so long to post an update here.  Wow, where did the month go?  Well we finished the IBM/Vette rear door and the APC Rack Air Containment System (RACS) and have spent the last two weeks configuring and testing the IBM Integrated Solution.  This is our first integrated cooling/compute system in the Chill Off and it was exciting to get this test underway.  We expect to wrap with this test Monday and move to our 8 rack APC Hot Aisle Containment (HACS) solution immediately after.  This will be our last of the chilled water solutions before we move to refrigerant!I am still working the schedule details for the refrigerant tests but we will most likely start with the Sun Glacier product and then move to the Clustered Systems solution.  Stay tuned for updates on that!